Skip to main content

How do I make variations/change orders on contract jobs?

How to make variations (change orders) to the contract on contract jobs

Matt Govett avatar
Written by Matt Govett
Updated yesterday

Audience: builders

Read/watch time: 10 mins

Article contents: Step-by-step video instructions on how to make variations/change orders for contract jobs; step-by-step written instructions on how to add variations to an invoice.

The following video covers how to create variations/change orders for contract jobs, if you're after variations/change orders on cost plus jobs head here:

Change Orders

Variations

Note: The adjustment type variation shown in this video is only available in Australia and New Zealand.

Steps for adding the variation/change order to an invoice

  1. In the "Outgoing Invoices" tab

  2. Note the Contract Total

  3. Note the Variations/change orders

  4. Click on the green "+" button to add a new invoice

5. In the invoice that appears, type in a description
6. Choose the variation/change order(s) you want to claim
​Note: this step has recently changed to allow you to choose a portion of the variation versus only the whole amount.
​
7. It is optional if you would like to claim any of the contract amount
8. Click "Save & Send", a pop up appears allowing you to choose the type of invoice, click "OK", then in the new screen you can add contacts and attachments, click "Send"

Did this answer your question?