Buildxact has traditionally only looked at estimated costs and actual costs when tracking costs. This approach gave a good view of how your costs were tracking relative to the set budget but didn't deal with looking forward at costs you'd committed to spend but hadn't actually spent yet. We've expanded functionality here now to give a better overall view of the job.
Here is a summary of the three types of cost at a job costing level:
Estimated: This is the budgeted spend on an item and have come from either the estimate or have been added in as the result of a variation/change order
Committed: This is the costs which are linked to sent purchase or work orders, they will also be populated automatically when the status of an order is moved straight to received.
Actual: This is the actual spend on an item, they are captured when you have a received or part received purchase order, or a completed work order
Watch the walkthrough
This short video walks through the committed and actual columns on the actual costing screen, and what happens when orders are sent, part received or received for a different amount.
Where can I see committed and actual costs?
Actual costing screen
The actual costing screen shows Committed and Actual columns alongside the estimated cost, so you can see both what you have committed to and what you have actually spent against each line item, category and for the job overall.
Turn off committed costs for line items
If you'd rather not see committed costs against each line item, you can turn them off. This only hides committed costs at the line item level. Committed costs still show in the category totals and the job totals at the bottom of the screen.
Open the job and go to the Actuals Costings tab.
Click the cog in the top right corner of the screen.
Untick Show committed costs for each actual item.
To show committed costs for line items again, tick the option back on.
Reports
Committed costs can also be compared against estimated costs on the Estimated vs Committed report. To open it, click the cog drop-down in the top right corner of the screen.
FAQ
What happens if I don't send purchase orders?
The committed and actual columns will still fill out. Without a sent purchase order, both values will be the same because they update at the point you enter the actual cost.
What happens if the received amount differs from the order?
Committed stays at the amount you ordered, and actual updates to the amount you received. For example, if you order an amount and then receive a larger amount, the committed cost remains lower and the actual cost is higher. This makes it easy to see when you have overspent against what you ordered.
Do committed costs decrease as the actual cost increases?
No. We want to be able to show the total estimated cost against the total committed cost, and total actual cost. Eg: If you budget $100 for an item and commit to $90, but spend $110 we want to show the journey rather than losing the committed figure in the process.
Any help?
As always, any feedback or questions, let us know. We are here to help.