  1. Click in the Schedule tab of the job.

  2. Click the More Actions button.

  3. Choose "Mark job as completed", and then a pop up will appear asking you to confirm.

  4. Click Confirm and all the tasks will change to green.

5. This will also move the job to Completed in the Navigation menu

Note: If you have incorrectly marked a job as 'Completed', you can set it back to 'In Progress' by changing any of the individual schedule tasks or by adding a new task and the schedule will recalculate.