This report will help you to track your actuals against your estimated budget

Written by Dan C

Open the job, and click onto the "Actuals Costings" tab.

  1. Click on the cog icon

  2. Print or email "Estimated vs Actuals" this will factor in the costs of PO's that have been receipted

  3. Print or email "Estimated vs Committed" this will factor in the costs of PO's that have been sent but not yet receipted

  4. Print or email "PC/PS items" to get a report of all items marked as Prime Costs or Provisional Sums

Note: Looking for a client-facing breakdown of estimated costs, actual costs, markup and invoicing? See the Cost Plus Breakdown Report. This report is only available for cost plus jobs.