If your job start date gets moved it is easy to change to start date.

  1. In the "Jobs" section under the "Schedule" tab click the cog icon located to the right side above your schedule.

  2. From the drop down menu click ''Set start date'' to set the new start date.

  3. A pop up will appear, click on the date to view a calendar and select a new date then click "OK".